HCPSS MPIA Request #2026-182

Requestor
Mark Zurada Esq.
Requested Information
Please send the final and compiled bid tabulation (bid tally), including all quantities and unit pricing for each bidder, for 'Talbott Springs Elementary School Utility Relocation' that was submitted on 02/19/2020. I believe the project number is '035.20.B4', but I could be mistaken. If so, please use the project name and date to lookup the responsive documents. We specifically request the line-item bid tabulation showing each material, quantity, unit, and unit price for every bidder. If no such line-item tally was created, please provide the full bid submissions from each contractor. A grand total sheet alone is not sufficient to satisfy this request unless it was a lump sum bid.
Date Received
Status
Complete
Response Notes

Responsive to this request, 035.20.B4 Talbott Springs Elementary School Utilities Relocation was awarded on March 26, 2020 (see PC-49): https://go.boarddocs.com/mabe/hcpssmd/Board.nsf/files/BMYLYS58E0CB/$file/03%2026%20202%20Bids%20%26%20Contracts%20BR.pdf. Our Procurement staff indicates this was a lump sum bid awarded based on the total base bid found in the report above.

*Some request language is summarized to include the requester's specific document requests and legally protected information (such as personally identifiable information of a student) or personal, defamatory and malicious content removed at the discretion of the school system.

**Responses containing legally protected information available only to the person of interest are omitted from the above report.

***Howard County Public Schools reserves the right to remove erroneous or outdated documents from this site.