Responsive to this request, beyond the records provided below, in regards to contract technical and cost proposals, such records no longer exist within the HCPSS Purchasing Office. Retention for documentation related to bids and requests for proposals as well as awarded bids and contract information within that office is for 10 years, which would be no later than 2010 after project completion.
While this is the document being used for the proposed renovation (not completed) it contains extensive information on the current building. As noted in this record, the prior renovation was a multi-phase Heating, Ventilation, and Air Conditioning (HVAC) systemic renovation performed during the summers of 1997, 1998, and 1999. This included Testing and Balancing (TAB) that would have been completed immediately following the HVAC installation work.